Projects

Project Name: Road Work Under ADB Project

Description: Rehabilitation & Upgradation of Sheorinarayan-Birra-Champa-Road (SH-9) (Package-16)

Contract Number & Year: 170/9040096/ADB/L-2/Civil/Contract/14,Raipur

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
11907 22-01-2015 21-01-2017 24 Months 4,168.97 -

Project Name: Road Work Under ADB Project

Description: Rehabilitation & Upgradation of Simga-Tilda-Kharora-Arang Road (SH-20) Package No. 05

Contract Number & Year: 15/2014-15 dated 20-03-2015

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
13695.88 19-03-2015 18-03-2017 24 Months 4,217.02 -

Project Name: Coal Transportation & Loading Work

Description: Hiring of Payloader & Tippers for Transportation of Coal from Baroud OC

Contract Number & Year: SECL/GM/RGH/SO(P&P)/WO/163/14/1402

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
5123.5 30-08-2014 30-06-2017 36 Months - 768.47

Project Name: Boundary Wall Work

Description: Construction of Plant Boundary Wall for LARA STPP

Contract Number & Year: 5500014225-025-1047

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
1616.88 12-09-2013 24-03-2015 18 Months 238.51 -

Project Name: Coal Transportation

Description: Coal Transportation from Various Coal Mines

Contract Number & Year: Various

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
4044 01-04-2017 31-03-2018 12 Months 1,848.80 -

Project Name: Civil Work

Description: Construction of Ash Dyke at Daripali, Super Thermal Power Project Odisa

Contract Number & Year: CS-9549-331-9-CS-LOA-6364

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
9266.51 08-06-2015 13-02-2018 32 MONTHS 5,436.95 -

Project Name: Coal Transportation & Loading Work

Description: Hiring of Payloader & Tippers for Transportation of Coal from Surface Stock Yard to Jampali OC

Contract Number & Year: SECL/BSP/CMC/917

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
2218.10 11-10-2015 25-02-2017 18 Months 914.99 -

Project Name: Coal Transportation & Loading Work

Description: Hiring of (a) Pay loader for mechanical transfer of Coal into Tippers at Stock Yard (b) Tippers for Transportation of Coal from Mahan II OCM Stock to Bhatgaon Wharfall Siding with minimum TPD 3000 Te. Per Day. Lead is 41 to 42 Kms.

Contract Number & Year: 6598/SAC

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
6,305.72 09-08-2015 07-08-2018 36 Months 1066.51 2284.35

Project Name: Civil Work

Description: Construction of Sheorinaryan Bypass Road

Contract Number & Year: 6598/SAC

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
2585.38 21-12-2016 20-09-2018 21 Months 783.32 1502.51

Project Name: Civil Work

Description: Construction of Civil Work including earthwork in formation for embakment and cutting, blanketing, Drains platforms, Approch Roads, Sand Hump, Foot Over Bridge, Permanent Works, Extension of Existing Bridges and level crossing and other allied works of private railway siding for proposed 3 MTPA Integrated Steel Plat for NMDC Ltd. at Nagarnar in chhattisgarh state.

Contract Number & Year: IRCON/2070/NMDC/PKG-IV/E-TENDER-CIVIL MISC & P-WAY WORKS/11

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
2328.09 10-12-2016 09-09-2017 9 Months 1950.50 -

Project Name: Civil Work

Description: Construction of Earthwork in formation, Muroom Blanketing, New Culverts, Retaing wall, Pathways Drains in connection with construction of private railway siding for the proposed 3.0 MTPA Integrated Steel Plant of NMDC LTD. At Nagarnar Near Jagdalpur

Contract Number & Year: IRCON/2062/NMDC/NISP/E-TENDER/EW&BR/PK-1

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
3724.38 25-01-2016 31-08-2016 8 Months 2138.44 -

Project Name: Civil Work

Description: Constrcution of Major Bridges (Package-III) along with its approch road work with RE Wall tecgbuque on NTPC Lara MGR Railway siding project in Raigarh

Contract Number & Year: RITES/RPO/RIG/NTPC-LARA/PKG-III/BACK BONE-AHMEDABAD/LOA-16/547

Value of Contract(Rs. Lakhs) Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
8746.62 15-03-2016 14-09-2017 18 Months 5207.40 3170.76

Project Name: Civil Work

Description: Construction of main Canal from ch 375 to 605 & 27 Nos. Canal Structures of Darbekera Diversion scheme of Bagbahra Block in Mahasamund distt.

Contract Number & Year: W.O. No.4506/SAC/Work Order/2016-17 Dtd. 25.10.2016

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
1189.67 31-10-2016 30-10-2017 12 Months 874.27 -

Project Name: Civil Work

Description: Construction of Urga-Hati road section from Existing Chainage km 0.000 to 46.835

Contract Number & Year: 1528/CGRDC/2017 DTD.20.06.17

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
9702.66 20-06-2017 19-09-2018 16 Months(485 days) 3638.50 6064.16

Project Name: Civil Work

Description: Construction of Pasan Pipariya Kodghar Dullapur mod Road section from km 0.000 to 32.320

Contract Number & Year: 1530/CGRDC/2017 DTD.20.06.17

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
6742.03 20-06-2017 19-09-2018 16 Months(485 days) 2528.26 4213.77

Project Name: Civil Work

Description: Ash Filling with soil covering near pond

Contract Number & Year: 8500002039 DTD.17.07.17

Value of Contract Date of Issue of Work Order Date of Issues Stipulated Stipulated Date of Completion Work Anticipated to be Done in the FY 2017-18 Work Anticipated to be Done in the FY 2018-19
2430.7 17-07-2017 16-03-2018 8 Months(240 Days) - 2430.70